Lighting Tease

Way more has happened at the house since last update, but I have run out of room on my phone for pictures so here two pictures I was able to squeeze on :)


Waiting for the plumber to hook up sinks, toilets, etc. Mirrors. Appliances. Grout kitchen backsplash. Carpet. Sprinkling and hydro seed. 
Otherwise I think pretty much everything else is done! (These last few weeks are definitely feeling like the longest..)

Thursday, September 25, 2014

Paint and flooring!

These last few weeks are starting to feel like they are going especially slow.. Other than the fact we are missing final plumbing- this house is starting to feel like we could pretty much move in! (Well, I guess we need carpet, door handles, appliances, and a few other things, but meh)

 Cabinets, backsplash, kitchen and bathroom flooring! Trim, woodwork, and doors also got their final coats. Loooove!
Also the front door is in the middle of being stained, walls are being painted, and the driveway got poured. Ek!
Landscaping, exterior trim painting, exterior pillars, final plumbing and electrical, appliances, and carpet are all that we have left! We are hoping to be in by the end of October, at the latest. #soready :)

Tuesday, September 9, 2014

Trim and more

Love the latest progress!
Trim still needs to be painted and front door stained. Lots of progress inside though too!
Trim and doors started last week


And yesterday: cabinets!



Less than two months til move in. Can't wait :)

Saturday, August 16, 2014

Siding Up

This was the siding as of at least a week ago? (I was hoping they would get the verticle siding up before I posted this, so of course they will do that tomorrow)

White! And guess what the front trim is supposed to be? White! I guess they paint that later :) We are so creative huh?!
Mudding has also been done for over a week.

Other than starting to install the furnace, I can't tell a single thing that got done this week :/.
In other news, we recently picked out flooring, counters, and the kitchen backsplash.
Here's a glimpse at the kitchen. 
Can't wait to see it all installed! Next step: cabinets and trim. Let's go!

Wednesday, July 30, 2014

Walls

We have walls.
And ceilings.
And it is starting to feel like a house.
They also built the back deck today.
And poured the front porch.
It was a busy house today!

Tuesday, July 29, 2014

Warming up

With rough-ins and their inspections finally done, we are moving on to another big step: insulation and drywall!
It was so nice to see something other than wood or wires finally. 

The drywall was delivered today too. Look at how big some of the sheets are!
The tub and showers were installed a few weeks ago. And the garage floor a little bit ago too.

Can't wait to see that drywall up!

Sunday, July 6, 2014

Windows and other progress

It has been over a week since I saw our house due to vacation/ holiday time.
We recently got windows, our front door, and the beginning of a roof.


The front door still needs to be stained.
Inside was some progress as well: archways finished, ducts started.

(Looking in to dining room from the living room)

(Kitchen)

(Looking in to living room from kitchen)

(Office)

(Stairs to second floor)

(Upstairs)